Sequence around business dependencies and failure consequences, not the loudest workstream or the easiest completion metric.
Start with a small number of business outcomes—employees can work, orders can flow, customers can receive support—and map the enabling dependencies. Identity, connectivity, security monitoring, data, application interfaces, and support ownership often cross workstream boundaries.
For each proposed migration wave, record its prerequisites, business blackout periods, acceptance tests, rollback conditions, and accountable decision-maker. Then ask: if this wave slips, what else moves? If it fails, can the business continue safely?
An application may be technically ready while its identity integration, reporting feed, or support team is not. Treat that as a dependency problem, not permission to migrate and repair afterward. Escalate choices between speed, continuity, cost, and value capture with options and consequences—not simply a red status.
Discussion prompt: Which cross-workstream dependency most often changes your integration sequence?